THE GRAND MIDORI ORTIGAS – AS OF FEBRUARY 2026

THE GRAND MIDORI ORTIGAS

Percentage of Completion:

THE GRAND MIDORI ORTIGAS – AS OF FEBRUARY 2026

Tower 1 – 100%

Tower 2 – 95.84%

 

THE FOLLOWING ARE ONGOING WORKS FOR THE GRAND MIDORI ORTIGAS:

– Completion of Exterior Painting

– Submission of RMC, rebar and DPT test results

– Completion of Roof Crown

– Meralco Power Energization

– Ongoing Waterproofing Works

– Endorsement of Residential Units to FLI-POG

– Endorsement of BOH and Residential Hallway

– FDAS with Mechanical and Fire Protection Works

– Completion of Unit J and K

 

License to sell:

HLURB LS NO.: 034640

Project Location: Exchange Road corner Jade Drive, Ortigas Center, Pasig City

Developer: Federal Land Inc.

Owner: Federal Land Inc.

Completion Date: Tower 1 – October 2024

 
 
 