THE GRAND MIDORI ORTIGAS – AS OF FEBRUARY 2026
- Katrina Verbo
- Mar 11
- 1 min read
By: Melecio Martin G. Arranz IV

THE GRAND MIDORI ORTIGAS
Percentage of Completion:
THE GRAND MIDORI ORTIGAS – AS OF FEBRUARY 2026
Tower 1 – 100%
Tower 2 – 95.84%
THE FOLLOWING ARE ONGOING WORKS FOR THE GRAND MIDORI ORTIGAS:
– Completion of Exterior Painting
– Submission of RMC, rebar and DPT test results
– Completion of Roof Crown
– Meralco Power Energization
– Ongoing Waterproofing Works
– Endorsement of Residential Units to FLI-POG
– Endorsement of BOH and Residential Hallway
– FDAS with Mechanical and Fire Protection Works
– Completion of Unit J and K
License to sell:
HLURB LS NO.: 034640
Project Location: Exchange Road corner Jade Drive, Ortigas Center, Pasig City
Developer: Federal Land Inc.
Owner: Federal Land Inc.
Completion Date: Tower 1 – October 2024